Appropriate plans, specs, etc., must be submitted in accordance with instructions from the
Building Commissioner or Pasadena Hills Municipal Code.
PLEASE ALLOW 5 - 7 working days for approval.
Numbers to Inquire:
| Approval of Permits** |
Inspections |
Inquiries |
Building Commissioner
or 382-4453 (leave a message) |
Building Inspector
210-7771 (daytime cell) |
City Office Manager
382-4453 |
** Under some circumstances approval from the Historic Preservation Committee may be necessary.
For Office Use Onlv
DATE APPROVED BY BLDG. COMM. _____________________________ PERMIT #_____________________________
ISSUE DATE: ______________________Permit Fee ______________ Payment Type___________
| Work Type |
Description |
Fee |
| Occupancy |
House or Apartment Occupancy |
$60.00 |
| |
| Building Permits |
Air Conditioning-Window Units |
1 - Exterior |
$17.50 |
| Decks |
1 - Piers 2 - Framing 3 - Final |
$52.50 |
| Driveways |
1 - Form work 2 - Pour/ Final |
$35.00 |
| Fences |
1 - Footings for Post 2 - Final |
$35.00 |
| Garages |
1 - Foundation 2 - Concrete Pour 3 - Framing/ Sheathing 4 - Exterior Final |
$70.00 |
| Interior Renovations |
1 - Demolition 2 - Plumbing/ Electrical 3 - Final |
$52.50 |
| Roofing |
1 - Tear Off 2 - Final |
$35.00 |
| Room Additions |
1 - Foundations 2 - Concrete Pour 3 - Framing/ Sheathing 4 - Interior Electrical/ Plumbing |
$87.50 |
| Satellite Dishes |
1 - Exterior |
$17.50 |
| Sidewalks/ Walkways |
1 - Form work 2 - Final |
$35.00 |
| Siding |
1 - Existing Exterior |
$17.50 |
| Walls, Retaining |
1 - Form work 2 - Final |
$35.00 |
| Walls, Exterior |
1 - Form work 2 - Final |
$35.00 |
| |
| Other |
| New Residential |
|
1 - Underground Utilities |
$210.00 |
| 2 - Footing Excavation/ Pour |
|
| 3 - Foundation Form Work/ Pour |
| 4 - Slab Re-bar/ Pour |
| 5 - Framing |
| 6 - Sheathing / Decking |
| 7 - Roofing |
| 8 - Utility Rough In |
| 9 - Exterior Finish/ Brick & Siding |
| 10 - Interior Drywall |
| 11 - Final Exterior |
| 12 - Final Interior |